
| Our Achivements |
| |
| |
|
The Odisha Renewable Energy Development Agency (OREDA) was established during 1984 under the Science and Technology Department, Government of Odisha with a view to promote research & development and popularize Non-Conventional and Renewable Sources of Energy in the State.
Since its inception ,OREDA has provided renewable energy solutions to more than 2.00 lakh households in the state by providing photovoltaic power plants, home light systems , street light systems, Biomass gasifiers and Biogas plants.
VISION
Provision of minimum illumination to all Remote Un-electrified Villages by 2012.
Increase the share of Renewable Energy to 10% of the total power mix by 2020.
Accelerated use of RE Technology in all sectors of economy.
Major Programs being implemented by OREDA:
• Remote Village Electrification
• Decentralized Distributed Generation
• Renewable Energy Power Projects
• Off-grid Solar Power Projects
• National Biogas and Manure Management Program
• Solar Photovoltaic Program
• Energy plantation and Bio-diesel production
Remote Village Electrification Program:
The Remote Village Electrification Program of Odisha began in the year 2006-07. So far electrification of 589 villages is complete and the same for 11 villages is under progress. During the current financial year 770 more villages have been sanctioned for which work orders have been placed on M/s Central Electronics Limited and M/s Bharat Electronics Limited on 29.6.2011 and 12.7.2011 respectively. The firms have communicated their acceptance of the order and are arranging to send materials by 4th week of August and start installation of systems in the first week of September. It has been scheduled to complete the work by end of December 2011.
Besides, the State Energy Department and REC have communicated a list of 530 more villages where survey is now under progress. DPRs will be sent to MNRE in phases so as to complete the lot by October 2011. Upon sanction it is expected to complete the project by 31st March 2012.
During a review taken by Hon’ble Chief Minister on 5.8.2011 it was decided that all those villages which were programmed for coverage under RGGVY but could not be taken up due to want of forest clearance should also be covered under RVEP. It is expected that about 300 to 400 villages could come under this category. Once the firm list is available survey and DPR preparation work will be taken up forthwith.
Year wise status of implementation of projects:
| FY |
No. of villages sanctioned |
No. of villages dropped due to grid connectivity and other reasons |
No. of villages completed |
Villages under progress As on 8.8.2011 |
Program for completion |
| 31st Aug ‘11 |
15th Sep’11 |
2006-07 |
197 |
5 |
185 |
7 |
5 |
2 |
2007-08 |
0 |
0 |
0 |
0 |
0 |
0 |
2008-09 |
91 |
4 |
86 |
1 |
0 |
1 |
2009-10 |
371 |
50 |
318 |
3 |
1 |
2 |
Total |
659 |
59 |
589 |
11 |
6 |
5 |
Note:
Solar Power plants are under installation in all these 11 villages. Civil works in most cases is complete. Erection of solar power plant, LT distribution line and house wiring is under progress. In village Tuluka of Angul District BEL has not yet sent the power plant materials although the rest of the works is complete. BEL has been requested to send the same at once and complete the work. Similarly in Madhichuan village in Balasore district the work was stopped half way due to want of forest clearance as the area is frequented by elephant. After agreeing to use sheathed cables in place of open conductors the matter was resolved and work is under progress. Three of the villages in Sundergarh district have become highly inaccessible due to incessant rains for which work had to be stopped half way. Work in these villages is expected to resume in the first week of September.
2010-11 Program:
During 2010-11 a total of 770 villages in 8 districts have been sanctioned by MNRE, GOI vide sanctioned Order No 21/5/2010-11/RVE dated 25.2011 and 21/09/2010-11/RVE dated 29.3.2011 . The total financial outlay of the program is Rs.3465 lakhs out of which Central Financial Assistance is Rs.2906 lakhs.
Following tender the work of these villages have been distributed between M/s CEL and M/s BEL in the following manner.
DISTRIBUTION OF WORK BETWEEN BEL & CEL UNDER RVEP-2010-11
BEL,KOLKATA |
Sl No |
District |
No. of village |
No. of HLS |
No. of SLS |
| 1 |
Kandhamal |
161 |
4382 |
421 |
| 2 |
Nayagarh |
37 |
821 |
84 |
| 3 |
Rayagada |
151 |
5063 |
470 |
|
TOTAL |
349 |
10266 |
975 |
|
CEL,SAHIBABAD |
| Sl No |
District |
No. of village |
No. of HLS |
No. of SLS |
| 1 |
Angul |
24 |
1016 |
103 |
| 2 |
Debagarh |
17 |
510 |
48 |
| 3 |
Rayagada |
233 |
6291 |
611 |
| 4 |
Sambalpur |
27 |
714 |
69 |
| 5 |
Mayurbhanj |
11 |
521 |
46 |
| 6 |
Gajapati |
109 |
3374 |
318 |
| |
TOTAL |
421 |
12426 |
1195 |
| |
GRAND TOTAL |
770 |
22692 |
2170 |
Note:
Out of the above, orders for 51 villages to CEL and 8 Villages to BEL were given earlier to the tender in old rates to accommodate the surplus systems on account of dropped villages and start work immediately.
Progress of work:
| S/N |
District |
No of Villages |
Status of constitution of VEC |
| till end of June |
during july |
Total |
Balance |
Schedule |
| Aug |
Sep |
Oct |
| 1 |
Gajapati |
109 |
46 |
43 |
89 |
20 |
20 |
0 |
0 |
| 2 |
Deogarh |
17 |
11 |
0 |
11 |
6 |
6 |
0 |
0 |
| 3 |
Rayagada |
384 |
98 |
74 |
172 |
212 |
50 |
100 |
62 |
| 4 |
Kandhamal |
161 |
10 |
28 |
38 |
123 |
40 |
40 |
43 |
| 5 |
Mayurbhanj |
11 |
11 |
0 |
11 |
0 |
0 |
0 |
0 |
| 6 |
Nayagarh |
37 |
5 |
17 |
22 |
15 |
15 |
0 |
0 |
| 7 |
Angul |
24 |
24 |
0 |
24 |
0 |
0 |
0 |
0 |
| 8 |
Samabalpur |
27 |
5 |
2 |
7 |
20 |
10 |
10 |
0 |
| |
Total |
770 |
210 |
164 |
374 |
396 |
141 |
150 |
105 |
New program:
Apart from the above 770 villages the State Energy department and REC have given a list of 530 villages where survey is under progress. The details are given below:
New villages identified for coverage during 2011-12 in in LWE Districts
| Sl No
|
District
|
No. of Villages Identified
|
Remarks
|
| 1
|
Keonjhar
|
96
|
LWE
|
| 2
|
Sundergrah
|
89
|
LWE
|
| 3
|
Kalahandi
|
137
|
LWE
|
| 4
|
Malkangiri
|
47
|
LWE
|
| 5
|
Nuapada
|
10
|
LWE
|
| 6
|
Bolangiri
|
2
|
LWE
|
| 7
|
Nawarangpur
|
4
|
LWE
|
| 8
|
Deograh
|
6
|
LWE
|
| 9
|
Koraput
|
139
|
LWE
|
|
Total
|
530
|
LWE
|
| 10
|
Ganjam
|
73
|
Non -LWE
|
| 11
|
Angul
|
1
|
Non - LWE
|
| 12
|
Bargarh
|
2
|
Non -LWE
|
| 13
|
Khurda
|
3
|
Non -LWE
|
| 14
|
Total
|
79
|
Non -LWE
|
|
|
Grand Total
|
609
|
|
Year wise physical &Financial Achievement
Physical and financial achievement for FY 2006-07
| Villages sanctioned |
197 |
| Villages completed |
185 |
| Villages dropped |
05 |
| Villages under progress |
07* |
| Total Amount sanctioned by MNRE (Rs) |
11,68,00,044 |
| Amount released |
9,95,68,172 |
| Amount to be refunded on account of dropped villages |
60,78,610 |
| Actual amount available for expenditure |
9,34,89,562 |
| Expenditure incurred |
7,87,46,780 |
| Balance amount available |
1,47,42,782 |
| UC submitted |
6,84,32,344 |
| Percentage of expenditure |
84.23 % |
Physical and financial achievement for FY 2008-09
| Villages sanctioned |
91 |
| Villages completed |
86 |
| Villages dropped |
04 |
| Villages under progress |
01 |
| Total Amount sanctioned by MNRE (Rs) |
3,44,02,100 |
| Amount released |
2,40,81,000 |
| Amount to be refunded on account of dropped villages |
32,01,068 |
| Actual amount available for expenditure |
2,08,79,932 |
| Expenditure incurred |
2,38,67,364 |
| Balance amount available |
(-) 29,87,432 |
| UC submitted |
2,38,67,364 |
| Percentage of expenditure |
114.30 |
Physical and financial achievement for FY 2009-10
| Villages sanctioned |
371 |
| Villages completed |
318 |
| Villages dropped |
50 |
| Villages under progress |
03* |
| Total Amount sanctioned by MNRE (Rs) |
24,37,06,436 |
| Amount released |
17,05,92,000 |
| Amount to be refunded on account of dropped villages |
4,48,09,910 |
| Actual amount available for expenditure |
12,57,82,090 |
| Expenditure incurred |
11,34,34,005 |
| Balance amount available |
4,01,22,287 |
| UC submitted |
11,34,34,005 |
| Percentage of Expenditure |
90.18% |
Abstract of physical and financial achievement up to 2009-10
| Villages sanctioned |
659 |
| Villages completed |
589 |
| Villages dropped |
59 |
| Villages under progress |
11 |
| Total Amount sanctioned by MNRE (Rs) |
39,49,08,580 |
| Amount released |
29,42,41,172 |
| Amount to be refunded on account of dropped villages |
05,40,89,588 |
| Actual amount available for expenditure |
24,01,51,584 |
| Expenditure incurred |
21,60,48,149 |
| Balance amount available |
05,18,77,637 |
| UC submitted |
16,79,59,511 |
| Percentage of Expenditure |
89.96% |
2010-11
| Villages sanctioned |
770 |
| Villages completed |
33 |
| Villages dropped |
0 |
| Villages under progress |
0 |
| No. of villages for which work orders placed |
770 |
| Total Amount sanctioned by MNRE (Rs) |
33,73,98,480 |
| Amount released |
23,60,20,405 |
| Expenditure incurred |
81,25,032 |
| Balance available |
22,78,95,373 |
| Percentage of Expenditure |
3.44% |
Year wise coverage of Remote Villages
|
| |
ACHIEVEMENTS OF OREDA UPTO 30.11.2008
Geographical spread of remote villages

Year wise- District wise coverage of households
| Sl No. |
District |
Households covered |
| 2006-07 |
2008-09 |
2009-10 |
2010-11 |
Total |
| 1 |
Gajapati |
860 |
22 |
0 |
3238 |
4120 |
| 2 |
Keonjhar |
1333 |
132 |
1428 |
0 |
2893 |
| 3 |
Sundergarh |
2516 |
0 |
3489 |
0 |
6005 |
| 4 |
Kalahandi |
2861 |
95 |
2834 |
0 |
5790 |
| 5 |
Nayagarh |
0 |
776 |
0 |
796 |
1572 |
| 6 |
Balasore |
0 |
130 |
0 |
0 |
130 |
| 7 |
Angul |
0 |
200 |
193 |
999 |
1392 |
| 8 |
Kandhamal |
0 |
9 |
0 |
4206 |
3895 |
| 9 |
Nuapada |
0 |
20 |
0 |
0 |
20 |
| 10 |
Malakangiri |
0 |
128 |
0 |
0 |
128 |
| 11 |
Rayagada |
0 |
80 |
1765 |
10963 |
12605 |
| 12 |
Mayurbhanj |
0 |
228 |
2635 |
498 |
3361 |
| 13 |
Bolangir |
0 |
0 |
56 |
0 |
56 |
| 14 |
Nawarangpur |
0 |
0 |
78 |
0 |
78 |
| 15 |
Deogarh |
0 |
0 |
0 |
492 |
492 |
| 16 |
Sambalpur |
0 |
0 |
0 |
685 |
685 |
| |
TOTAL |
7570 |
1820 |
12478 |
21877 |
43745 |
 |
|
 |
| Vill. Pichiliguda, Bissamkatak, Rayagada |
|
An illuminated kitchen in Jamuani
vill,Jashipur , Mayurbhnaj . |
 |
|
 |
Solar Power Plant in Kiapadar,
Rampur, Kalahandi
|
|
A solar street light in Badisol vill, Th.
Kolnara, Rayagada |
 |
|
 |
| Improved quality of life |
|
Extended working hours |
 |
|
 |
| Evening meeting |
|
Children studying under the light |
 |
| |
Potential of Renewable Energy in Odisha
| S/N |
Renewable Energy Source |
Gross Potential (MW) |
Feasible Potential (MW) |
| 1 |
Solar Photovoltaic |
40,000 |
8000 |
| 2 |
Solar Thermal |
10000 |
2000 |
| 3 |
Wind |
1700 |
910 |
| 4 |
Biomass-paddy husk |
300 |
250 |
| 5 |
Biomass – paddy straw |
600 |
250 |
| 6 |
Other Biomass |
800 |
250 |
| 7 |
Biodiesel |
300 |
150 |
| 8 |
Small Hydro Project |
120 |
120 |
|
Total |
53820 |
11820 |
Solar Power Program (on grid Projects)
• The state of Odisha receives an average solar insolation of about 5.5 kW per Sq meter.
• At this rate the average capacity utilization factor is expected to be about 19%
• Keeping this in view the State offers a levellized tariff of Rs 17.80 per kwh over a period of 25 years.
• At present 8 solar power plants each of 1 MW capacity are under installation in the state under the RPSSGP scheme.Two of these projects have been commissioned in bargarh and Cuttack districts. The balance will be commissioned by Septmeber 2011.
• The State Distribution utilities will be having solar obligation of about 15 to 20 MW per year till 2015-16 and thereafter depending upon the capacity addition in thermal power this would increase further. The State Technical Committee for RE Power projects has resolved to invite RFPs for a total of 25 MWs for fulfilling the RPO of GRIDCO.
Besides, OREDA has been designated as the State Nodal Agency for Administration of RPO in the State by the OERC. Under this function several obligated entities (those having Captive Generation Plants of more than 5 MW or drawing more than 5 MW power from open access) have been identified in the state and actions are being initiated to help them fulfill their solar as well as non solar obligations as determined by the OERC.
Upcoming Solar Power Projects
|

|
| Wind Power Generation Program |
In 1998 C-WET however published wind data of 6 potential sites where commercial exploitation was possible. The details of the sites are as under: |
| S/ N |
Site |
Mean wind power density |
| 1. |
Chandipur |
315 W/sqm |
| 2 |
Chatrapur |
264 W/sqm |
| 3 |
Damon Jodi |
250 W/sqm |
| 4 |
Gopalpur |
265W/sqm |
| 5 |
Paradeep |
289 W/sqm |
| 6 |
Puri |
214 W/sqm |
|
However due to absence of a state wind policy, developers did not show much interest for harnessing wind power in the state.
In December 2005 after announcement of the Renewable Energy Policy of the State when developers showed interest to set up wind power projects it was observed that suitable land in the above 6 sites is no more available due to various reasons.
OREDA therefore made attempts to identify new sites around the same old sites under the MNRE scheme “Wind Resource Assessment through Private Developers for subsequent development of wind farms” in the following sites |
| Sl.No |
Name of the company |
Place |
District |
No. of locations |
Date of commencement |
Data available for |
| 1. |
M/s Suzlon Infrastructure ltd,Hyderabad |
Dhamara |
Bhadrak |
1 |
February,2007 |
August,2007 to January, 2010. |
| 2 |
-do- |
Chatrapur |
Ganjam |
1 |
-do- |
- |
| 3 |
-do- |
Nabarangpur |
Nabarangpur |
1 |
-do- |
- |
| 4 |
-do- |
Puri |
Puri |
1 |
-do- |
Januaary,2008 to January, 2010. |
| 5 |
-do- |
Damonjodi south |
Koraput |
1 |
-do- |
July, 2007 to June, 2008. |
| 6 |
-do- |
Damonjodi North |
Koraput |
1 |
-do- |
- |
| 7 |
-do- |
Chandipur |
Baleswar |
1 |
-do- |
- |
| 8 |
-do- |
Paradeep |
Jagatsingpur |
1 |
-do- |
- |
| 9 |
Centre for Wind Energy Technology (C-WET), Chennai |
Daitari |
Keonjhar |
1 |
October,2009 |
- |
| 10 |
-do- |
Gandhamardhan |
Keonjhar |
1 |
-do- |
- |
| 11 |
-do- |
Khandadhar |
Sundergarh |
1 |
-do- |
- |
| 12 |
M/s ReGen Powertech ltd,Chennai |
Sambalpur |
Sambalpur |
1 |
August,2010 |
- |
| 13 |
-do- |
Puri |
Puri |
1 |
-do- |
- |
| 14 |
-do- |
Khurda |
Khurda |
1 |
-do- |
- |
| 15 |
-do- |
Kandhamal |
Kandhamal |
1 |
-do- |
- |
| 16 |
-do- |
Kalahandi |
Kalahandi |
1 |
-do- |
- |
|
| |
New Proposals for setting up wind farms
|
In the mean while, M/s Suzlon Infrastructure ltd, Hyderabad has submitted a Detailed Project Report (DPR) for setting up of 51.25MW Wind Power project at Panchapatmali sites of in Koraput district. Similarly, M/s REGEN has submitted DPR for a 21 MW wind farm in the same Damanjodi area. Both the projects are under consideration of the State Technical committee.
Wind Resource Assessment in Odisha.
|
 |
Fresh initiatives:
As per the recent wind atlas published by C-WET the total wind power potential of Odisha has been estimated at 910 MW. C-WET has also provided the coordinates of 28 sites for taking up fresh wind resource assessment studies. The village details of these locations have been collected from Odisha Space Application Centre and acquisition of land for setting up met masts is in progress.

|
Biomass Power Projects
Estimated Potential : 300 MW
Implementation agreements signed:138 MW.
Total No. of Projects : 11
Total investment : 710 crores.
20 MW project by Shalivahana Green Energy in Nimidah village of Dhenkanal district is expected to be commissioned in two
months time.
Other projects are at various levels of implementation.
 |
National Biogas and Manure Management Program (NBMMP)
The state of Odisha has a potential of about 6.00 lakhs domestic biogas plants. So far about 2.5 lakhs domestic biogas plants have been installed. For the current year 2010-11 a target of 8000 and .biogas plants has been accepted. Out of this so far 6050 plants have been completed and about plants are at different levels of construction. The district –wise break up of completed plants is as under. Besides construction of plants 96 users’ training programs and two construction –cum-maintenance training programs have been completed as against the targets of 200 and 5 nos programs respectively. |
| Slno |
District |
Target |
Achievement |
Users Training |
Masons Training |
| 1 |
Angul |
350 |
222 |
09 |
- |
| 2 |
Balasore |
110 |
75 |
03 |
- |
| 3 |
Bargarh |
400 |
262 |
07 |
- |
| 4 |
Bhadrak |
300 |
106 |
07 |
- |
| 5 |
Bolangir |
150 |
120 |
10 |
01 |
| 6 |
Boudh |
25 |
25 |
02 |
- |
| 7 |
Cuttack |
800 |
700 |
18 |
- |
| 8 |
Deogarh |
150 |
65 |
03 |
- |
| 9 |
Dhenkanal |
200 |
84 |
05 |
- |
| 10 |
Gajapati |
200 |
150 |
05 |
- |
| 11 |
Ganjam |
350 |
260 |
08 |
- |
| 12 |
Jagatsinghpur |
450 |
350 |
10 |
- |
| 13 |
Jajpur |
300 |
200 |
10 |
|
| 14 |
Jharsuguda |
300 |
300 |
07 |
01 |
| 15 |
Kalahandi |
100 |
66 |
02 |
- |
| 16 |
Kandhamal |
25 |
10 |
01 |
- |
| 17 |
Kendrapara |
350 |
250 |
08 |
01 |
| 18 |
Keonjhar |
400 |
300 |
10 |
- |
| 19 |
Khurda |
270 |
222 |
06 |
- |
| 20 |
Koraput |
450 |
380 |
15 |
- |
| 21 |
Malkangiri |
30 |
21 |
02 |
- |
| 22 |
Mayurbhanj |
50 |
50 |
02 |
01 |
| 23 |
Nawaranagpur |
300 |
140 |
07 |
01 |
| 24 |
Nayagarh |
50 |
15 |
02 |
- |
| 25 |
Nuapara |
40 |
36 |
01 |
- |
| 26 |
Puri |
350 |
362 |
05 |
- |
| 27 |
Rayagada |
200 |
100 |
05 |
- |
| 28 |
Sambalpur |
350 |
296 |
08 |
- |
| 29 |
Sonepur |
150 |
132 |
02 |
- |
| 30 |
Sundargarh |
800 |
751 |
20 |
- |
|
TOTAL : |
8000 |
6050 |
200 |
05 |
|
Off-grid Solar Power Projects
|
A 50kWp roof top Solar PV Power Plant has been sanctioned by MNRE during 20010-11.
The same is proposed to be installed on the roof top of North Annex Building of Odisha Secretariat
The power from this plant will be supplied dedicatedly to lawn/garden lights, street lights, 3rd floor conference hall.
Excess power will flow in to the main distribution panel of the building.
Total saving on this account would be about Rs 1,80,000/- (45000 units)per annum.
A 2kW solar power plant has been commissioned in Eco-tourism complex in Berhampura island in Chilika lake.
A 650 watt power plant has been commissioned in Badatamera Sevasharm in Nabarangpur district. The power plants provides illumination to 10 rooms and powers a TV for use by the inmates of the ashram. The project was inaugurated by Hon’ble Minister, science and Technology Department on 26.8.2010.
Project proposals for installation of Solar Power Plants in Raj Bhawan, Bhubaneswar, Sun Temple, Konark etc. are under preparation.
|
| Energy Plantation and Bio-diesel Production |
Energy Plantation and Bio-diesel Production was adopted by the State during 2007-08 with a view to make effective use of wastelands for cultivation of Jatropha and other suitable non-edible oilseeds as well as to generate employment opportunities in rural areas.
|
Coverage of jatropha plantation:
2008-09 : 4847 Acres
2010 -11: 3338 Acres
Plantation activity is continuing through NREGS |
National Biogas Manure Management Programme (NBMMP).
-
Total No. of Biogas plants constructed up to 2007-08 : 2,05,381.
-
A total number of 4000 family type biogas plants, 5 Nos. CMC/Refresher training course and 200 Nos. User’s courses have been allocated to the state for the year 2008-09. Training programmes and construction of Biogas plants under progress.
- Solar Photovoltaic Programme.
- The SPV programme of MNRE for the year 2007-08 continued up to 31.10.2008.
- Supply and installation of 441 Nos. of SPV Home Light Systems and 159 Nos. SPV Street Light Systems have been made under the programme.
- Total achievement under the programme are as follows.
SPV Home Light Systems : 5121 Nos.
SPV Street Light Systems : 5471 Nos.
SPV Power Plants : 26/74.516 KWp.
Solar Lanterns : 9603 Nos.
- Electrification of two remote villages namely, Udal and Tentulikhol in Kishorenagar block of Angul district have been completed by OREDA with installation of SPV LED Home Lighting Systems and Street Lighting Systems. The electrification works have been inaugurated by Hon’ble Minister Planning & Co-ordination and Science & Technology and Hon’ble Minister School and Mass Education on 9.7.2008.
- Proposal for electrification of Gunupur High School in Thuamul Rampur block of Kalahandi district with power supply through SPV Power Plant has been submitted to S & T Dept.
- Remote Village Electrification Programe.
-
Number of projects sanctioned by MNRE under RVEP-2006-07 : 197 (Gajapati-45, Keonjhar-22, Sundargarh-60, Kalahandi-70)
-
Number of villages electrified : 77 (Gajapati-44, Keonjhar-15, Sundargarh-10 and Kalahandi-8).
-
Electrification of the balance villages in Kalahandi and Sundargarh districts are under progress.
-
Survey of 246 unelectrified villages certified by REC Ltd. for electrification under RVEP and preparation of DPRs are in progress.
5. Village Energy Security Programme (VESP).
-
Number of VESP Projects sanctioned by MNRE, Govt. of India – 12.
-
Installation and commissioning of Biomass Gasifier power generating systems in 10 VESP projects have been completed and power supply to the villagers effected. Other components of the projects are in completion stage.
-
The test projects at Lundurupadar in Ganjam and Kandhal in Cuttack districts are in progress.
6. Research and Development Programme.
-
A joint research project by OREDA and OUAT on operation of the stationary engine on straight vegetable oil have been taken up.
-
A proposal for development of a tunnel dryer specific to drying of Kendu leaves, ginger, vegetables and other forest produce etc. have been submitted to S & T Dept. against the current year’s budget provision .
7. Wind Power Generation Programme
-
Project proposal for installation of 2 MW demonstration wind project at Panchpatmali Bauxite Mines of NALCO, Damanjodi has been submitted to MNRE, Govt. of India.
-
The power purchase agreement has been prepared and sent to NALCO for acceptance.
-
The officials of OREDA were deputed to the site at Damanjodi, NALCO for demarcation of the proposed site. The same has been done and the contour drawing has been submitted to NALCO for allocation of proposed land in favour of OREDA.
-
C-WET, Govt. of India has been requested to prepare the micro-siting report and DPR for the PPL Project.
-
C-WET, Govt. of India have been requested to take up wind resource assessment in Sambalpur, Ganjam and Keonjhar districts. The officials of C-WET have visited the site.
8. 110 KW Sunei Mini Hydel Project (MHP).
-
The project was commissioned and put to operation on 1st August 2007 and feeding power to the grid since then.
-
The project has generated more than 80,000 units of power since commissioning.
-
Agreement has been signed with GRIDCO for sale of power from the project.
-
The tariff for the purchase of power from the project has been submitted to OERC by GRIDCO for vetting.
9. Bio-fuels
-
The resolution on policy guidelines for raising energy plantations and bio-diesel production has been issued vide letter No.5345 dated 23.8.2007 of Science & Technology Department, Govt. of Odisha. The Gazette Notification of the policy guidelines has been made.
-
OREDA is nominated by Govt. of Odisha as the State Nodal Agency for bio-diesel development in the state and function as the single window for promotion and facilitation of all such projects.
-
The Ministry of Rural Development, Department of Land Resources, Govt. of India have sanctioned financial assistance of Rs.4.00 crores for raising Jatropha nursery in the State of Odisha through OFDC Ltd., Bhubaneswar. Out of the above financial assistance the State Govt. have decided to place Rs.2.00 crores with OREDA for raising Jatropha nurseries. An amount of Rs.1.98 crores have been sanctioned by the M.D., OFDC Ltd. and released Rs.98.00 lakhs.
-
The total physical target has been fixed as 66 lakhs seedlings.
-
Besides the above, Govt. in S&T Department have sanctioned and released Rs.2.00 crores during 2007-08 for raising Jatropha plantation for production of bio-fuel in 8 KBK districts.
-
Plantation of 1,00,377 Nos. Jatropha Curcus in Rayagada district, 81200 Nos. in Ganjam district and 1,48,400 Nos. in Kalahandi district have been verified and seedling cost has been released.
-
The action plan under the programme for the year 2008-09 is enclosed herewith.
-
Physical and Financial Achievement as on November, 2008.
S/N |
Item |
Target |
Achievement |
Expenditure |
1 |
Organization of Dist. Level Workshop |
4 |
1 |
0.50 |
2 |
Organization of Block Level Workshop |
40 |
10 |
2.50 |
3 |
Organization of farmers’ training programme |
100 |
100 |
5.00 |
3 |
Dist. level monitoring cell |
20 |
7.00 |
140.00 |
4. |
Subsidy for Plantation Programme |
15000
Acre. |
4264 |
0 |
5. |
Enumeration of TBOs |
8 Districts |
Nil |
0 |
6. |
Revolving fund for procurement of seeds |
LS |
Nil |
0 |
7 |
Setting up of demonstration Bio-diesel production centers |
20 |
Nil |
0 |
8 |
Printing of IEC material |
LS |
Nil |
Nil |
9 |
Misc. & contingencies |
LS |
Nil |
Nil |
|
Total |
|
|
148.00 |
Plantation Activities under Progress:
S/N |
District |
Area in Acre |
Status |
1 |
Angul |
70.82 |
Land identified, DPR under preparation |
2 |
Koraput |
271.00 |
DPR prepared and submitted to Bank |
3 |
Nowrangpur |
580.00 |
DPR prepared and submitted to Bank |
4 |
Keonjhar |
955.00 |
DPR prepared and submitted to Bank, Plantation Started |
5 |
Sundergarh |
100.00 |
DPR under preparation. |
|
Total |
6240.82 |
|
10. Municipal Solid Waste (MSW)
-
For management of MSW in all 103 ULBs of the State, OREDA already prepared the model DPRs and finalized the vendors for different collection and transportation equipments.
-
DPR for Solid Waste Management in Puri and Bhubaneswar Municipalities as per the JNNURM norms have been prepared through M/s Center for Environment Education (CEE) Ahmedabad and submitted to H&UD Dept., Govt. of Odisha.
11. Biomass Power Generation
- In principle clearance has been issued for 22 projects in 22 districts for a total capacity of 257 MW. Out of the above Detail Project Reports in respect of 15(Fifteen) projects have been received.
- State Technical Committee meeting was convened on 15.11.2008 for issue of Techno Economic Clearance for setting up of Biomass based power generating projects in different districts of the state.
12. Seminars and Symposia.
- One International Seminar on “Renewable Energy in Climate Change Mitigation” has been organized at Hotel Swosti Plaza, Bhubaneswar on 22.10.2008.
13. Clean Development Mechanism (CDM).
- OREDA has been declared as the State Nodal Agency for development of CDM projects in the state of Odisha by the Ministry of Forest and Environment (MOEF), Govt. of India.
- Three Project Design Documents (PDD) on Wind Power Project, Hydel and RVEP have been submitted to MOEF, Govt. of India for consideration. Besides another CDM activity report is also under preparation for assessing IDBI, World Bank carbon trading funds
14. ISO CERTIFICATION
- OREDA has taken steps for streamlining systems and procedures with the aim to increase organizational effectiveness so as to get Integrated Management System certified to ISO 9001-2000 and 14001-2004. Suggestions of the auditors and the certifying registrar would be incorporated to improve all round efficiency.
- The server and other computers with LAN have been put in place. Finger printing identification for attendance of the employees, internal messaging and file digitization of OREDA has been established.
- All the office processes are being carried out through Office Automation Software.
| PROGRESS OF DIFFERENT RENEWABLE ENERGY SCHEMES IMPLEMENTED BY OREDA |
Sl. No. |
Name of the Scheme |
Unit |
Cumulative Achievement Upto Oct. 2007 |
1 |
N.P.B.D. |
Nos. |
1,51,001 |
2 |
N.P.I.C. |
Nos. |
15,92,517 |
3 |
C.B.P./I.B.P. |
Nos. |
38 |
4 |
Biogas (F.T) |
Nos. |
1,97,733 |
5 |
Improved Chulla (FT)- |
Nos. |
21,01,600 |
6 |
Street Lighting System |
Nos. |
6,655 |
7 |
Home Lighting System |
Nos. |
4823 |
8 |
Solar Lantern |
Nos. |
9,719 |
9 |
SPV Power Plant |
Nos. |
63 |
10 |
Solar Cooker |
Nos. |
3495 |
11 |
Solar water Heating System |
Nos. |
141300 LPD |
12 |
Solar Distillation System |
Nos. |
1192.50 Lpd per day |
13 |
Solar Photo Voltaic |
- |
a) Street Lighting system |
Nos. |
5,182 |
- |
b) Home Lighting System |
Nos. |
4,333 |
- |
c) Solar Lantern |
Nos. |
9,402 |
- |
d) SPV Operated TV |
Nos. |
58 |
- |
e) SPV Pumping Systems. |
Nos. |
51 |
- |
f) SPV Power Plant |
KWp |
36.515 Kwp |
14 |
Solar Thermal Extension Program |
- |
a) S.W.D.S. |
LPD |
1,35,300 |
- |
b) S.D.S. |
LPD |
1,192.5 |
- |
c) Solar Cooker |
Nos. |
3,472 |
|